Construction Update

Project Progress Update at 16th October 2017

 

 

 

So far on site the following works have been completed:

  • Mobilisation and commissioning of on-site concrete batching plants
  • Gywdir Highway intersection upgrading works
  • Waterloo Road upgrading and new causeway works
  • Wind turbine components have started to arrive at Newcastle Port
  • Substation transformer 1A has been delivered
  • Substation transformer 1B has been delivered
  • Substation control room has been delivered
  • Substation switchroom has been delivered
  • New 330Kv Over head line works have commenced
  • 40km out of 47km of new internal roads constructed
  • 65 out of 75 wind turbine foundations completed
  • 35 out of 75 wind turbine foundations backfilled ready for turbine erection
  • 144km out of 245km of new underground cabling installed
  • Installation of bases and tower sections have commenced